note that, making a Gantt chart based directly on the issue tracker unfortunately feels non-trivial right now:
kiara referenced this pull request from kiara/fedi-goals2025-06-05 10:45:38 +02:00
@ -23,4 +20,0 @@
[M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
[M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed
I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing
@ -26,3 +20,2 @@
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed
[D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed
-- WP2 Vertical Hosting --
We can rename the workpackage I guess, but we can't remove past items since they have been done.
Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers
I recommend simplifying this to just the three stages (and possibly subdividing them if needed, but rather not): implementation, outreach, productive sample applications. Also as discussed, past work should stay in place because that already happened anyway.
@fricklerhandwerk
given now bars got removed, i presume this is about the UX item i'd wholesale greyed out - that one i reinstated now.
i tried these now, tho outreach sounds less like a phase, while the other two seem tangled up as well.. maybe not what they wanted to see? alternatively, drop this distinction too? 😶😅