initial gantt chart for proposal rewrite #33

Merged
kiara merged 8 commits from proposal-gantt into main 2025-06-12 17:23:38 +02:00
Owner

note that, making a Gantt chart based directly on the issue tracker unfortunately feels non-trivial right now:

  • weighted issues seems in PR still
  • gitea/forgejo seem to not yet offer progress bars for say milestones yet. right now we mostly use (hierarchically structured) issues. these support progress bars based on manually curated checkboxes, but that seems a bit more frail.
note that, making a Gantt chart based directly on the issue tracker unfortunately feels non-trivial right now: - weighted issues seems [in PR](https://github.com/go-gitea/gitea/pull/32086) still - gitea/forgejo seem to not yet offer progress bars for say milestones yet. right now we mostly use (hierarchically structured) issues. these support progress bars based on manually curated checkboxes, but that seems a bit more frail.
kiara added 1 commit 2025-06-05 10:41:33 +02:00
fricklerhandwerk was assigned by kiara 2025-06-05 10:41:45 +02:00
Niols was assigned by kiara 2025-06-05 10:41:45 +02:00
kiara added 1 commit 2025-06-05 11:16:28 +02:00
kiara added 1 commit 2025-06-05 11:57:44 +02:00
fricklerhandwerk reviewed 2025-06-06 11:39:15 +02:00
@ -23,4 +20,0 @@
[M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
[M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed

I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing

I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing
kiara marked this conversation as resolved
fricklerhandwerk reviewed 2025-06-06 11:40:04 +02:00
@ -26,3 +20,2 @@
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed
[D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed
-- WP2 Vertical Hosting --

We can rename the workpackage I guess, but we can't remove past items since they have been done.

We can rename the workpackage I guess, but we can't remove past items since they have been done.

Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers

Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers
kiara marked this conversation as resolved
kiara added 1 commit 2025-06-06 16:38:17 +02:00
kiara added 1 commit 2025-06-06 17:08:42 +02:00

I recommend simplifying this to just the three stages (and possibly subdividing them if needed, but rather not): implementation, outreach, productive sample applications. Also as discussed, past work should stay in place because that already happened anyway.

I recommend simplifying this to just the three stages (and possibly subdividing them if needed, but rather not): implementation, outreach, productive sample applications. Also as discussed, past work should stay in place because that already happened anyway.
kiara added 1 commit 2025-06-12 13:15:31 +02:00
kiara added 1 commit 2025-06-12 13:43:57 +02:00
Author
Owner

@fricklerhandwerk

past work should stay in place because that already happened anyway.

given now bars got removed, i presume this is about the UX item i'd wholesale greyed out - that one i reinstated now.

I recommend simplifying this to just the three stages

i tried these now, tho outreach sounds less like a phase, while the other two seem tangled up as well.. maybe not what they wanted to see? alternatively, drop this distinction too? 😶😅

@fricklerhandwerk > past work should stay in place because that already happened anyway. given now bars got removed, i presume this is about the UX item i'd wholesale greyed out - that one i reinstated now. > I recommend simplifying this to just the three stages i tried these now, tho outreach sounds less like a phase, while the other two seem tangled up as well.. maybe not what they wanted to see? alternatively, drop this distinction too? 😶😅
kiara added 1 commit 2025-06-12 13:54:54 +02:00
kiara changed title from WIP: initial gantt chart for proposal rewrite to initial gantt chart for proposal rewrite 2025-06-12 17:23:09 +02:00
Author
Owner

i wouldn't claim this to be perfect, but i'm fine with making new PRs if needed

i wouldn't claim this to be perfect, but i'm fine with making new PRs if needed
kiara merged commit 6514843244 into main 2025-06-12 17:23:38 +02:00
Sign in to join this conversation.
No reviewers
No labels
WP2
WP3
No milestone
No project
2 participants
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference: Fediversity/meta#33