Merge pull request 'initial gantt chart for proposal rewrite' (#33) from proposal-gantt into main

Reviewed-on: #33
This commit is contained in:
Kiara Grouwstra 2025-06-12 17:23:37 +02:00
commit 6514843244
4 changed files with 53 additions and 34 deletions

Binary file not shown.

Before

Width:  |  Height:  |  Size: 95 KiB

After

Width:  |  Height:  |  Size: 82 KiB

View file

@ -1,4 +1,5 @@
@startgantt
skinparam backgroundcolor transparent
<style>
ganttDiagram {
@ -12,7 +13,7 @@ ganttDiagram {
}
</style>
2024-12-20 to 2025-01-5 is closed
2024-12-20 to 2025-01-05 is closed
2025-07-01 to 2025-08-31 is closed
Project starts 2023-12-01
projectscale monthly
@ -20,47 +21,52 @@ projectscale monthly
[Reporting period 1] happens at 2025-05-31
Separator just at [Reporting period 1]'s end
-- WP1 Project Management --
[M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
[M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed
[M1 First ActivityPub presence] as [a1] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] as [a11] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
[M6 First Tech talk] as [a6] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] as [a7] starts 2024-07-31 and requires 7 days and is 100% completed
-- WP2 Vertical Hosting --
[D2.5 Technical architecture document] starts 2024-01-01 and ends 2024-03-29 and is 60% completed
[D2.7 Analyze investment on fediverse] starts 2023-12-01 and ends 2024-04-30 and is colored in Red
[D2.6 CI/CD setup] starts 2024-03-01 and ends 2024-10-31 and is colored in Red
[D2.4 Nix Packages and NixOS Services] starts 2024-05-01 and ends 2024-11-29 and is 67% completed
[D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29 and is 67% completed
[D2.2 Software Release beta environment] starts 2025-01-01 and ends 2025-12-31 and is 0% completed
[D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed
[D2.5 Technical architecture document] as [b5] starts 2024-01-01 and ends 2025-06-15 and is 90% completed
' [b5] is colored in Red
[D2.1 Implementation] as [b1] starts 2024-03-01 and ends 2026-11-30 and is 50% completed
[D2.2 Produce sample applications] as [b2] starts 2024-05-01 and ends 2026-11-30 and is 50% completed
-- WP3 Vertical Public organizations --
[D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 0% completed
[D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 0% completed
[D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c3]'s end and ends 2026-10-30 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c4]'s end and ends 2026-10-30 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c5]'s end and ends 2026-10-30 and is 0% completed
[D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 100% completed
[c1] is colored in Grey
[D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 100% completed
[c2] is colored in Grey
[D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[c3] is colored in Grey
[D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[c4] is colored in Grey
[D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[c5] is colored in Grey
[D3.6 Running Fediverse software for public organisations advisory] as [c6] starts at [c3]'s end and ends 2025-06-15 and is 100% completed
[c6] is colored in Grey
-- WP4 Open calls and grant management --
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed
[M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed
[M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed
[D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
[M2 Announcement open call] as [d2] starts 2023-12-29 and requires 7 days and is 100% completed
[M3 First open call opens] as [d3] starts 2024-02-01 and requires 7 days and is 100% completed
[M4 First batch of grantees selected] as [d4] starts 2024-03-29 and requires 7 days and is 100% completed
[D4.1 Overview of granted projects] as [d41] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
-- WP5 Enhancement and Usability --
[D5.6 Setup UX design testlab] starts 2023-12-01 and ends 2024-07-31 and is colored in Red
[D5.1 User requirement document] starts 2024-05-01 and ends 2024-08-30 and is colored in Red
[D5.2 UX design] starts 2024-09-02 and ends 2025-11-28 and is 0% completed
[D5.3 UX design implementation] starts 2025-12-01 and ends 2026-05-29 and is 0% completed
[D5.4 UX design user studies] starts 2026-05-01 and ends 2026-09-30 and is 0% completed
[D5.5 Design iteration and final release] starts 2026-10-01 and ends 2026-11-30 and is 0% completed
[D5.6 Setup UX design testlab] as [e6] starts 2023-12-01 and ends 2024-07-31 and is 100% completed
[D5.1 User requirement document] as [e1] starts 2024-05-01 and ends 2024-08-30 and is 100% completed
[D5.2 UX design] as [e2] starts 2024-09-02 and ends 2025-11-28 and is 100% completed
[D5.3 UX design implementation] as [e3] starts 2025-12-01 and ends 2026-05-29 and is 100% completed
[e3] is colored in Grey
[D5.4 UX design user studies] as [e4] starts 2026-05-01 and ends 2026-09-30 and is 100% completed
[e4] is colored in Grey
[D5.5 Design iteration and final release] as [e5] starts 2026-05-01 and ends 2026-11-30 and is 100% completed
[e5] is colored in Grey
-- WP6 Outreach and Dissemination --
[D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red
[D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 0% completed
[D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed
[D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
[D6.1 Communication strategy] as [f1] starts 2023-12-01 and ends 2024-01-31 and is 100% completed
[D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 100% completed
[D6.3 Communication report first period] as [f3] starts 2025-03-03 and ends 2025-04-30 and is 100% completed
[D6.4 Communication report second period] as [f4] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
[D6.5 Developer outreach] as [f5] starts 2025-01-01 and ends 2026-11-30 and is 10% completed
@endgantt

View file

@ -0,0 +1,13 @@
---
title: Fediversity work package interdependencies
---
flowchart
management["WP1: Project Management"]
vertical["WP2: Vertical Hosting"]
grants["WP4: Open calls and grant management"]
ux["WP5: Enhancement & Usability"]
dissemination["WP6: Outreach & Dissemination"]
management --> vertical & ux & dissemination & grants
vertical --> ux
vertical & ux & dissemination --> grants