meta/planning/gantt.puml

60 lines
3.3 KiB
Plaintext
Raw Normal View History

@startgantt
<style>
ganttDiagram {
task {
BackGroundColor GreenYellow
LineColor Green
}
undone {
BackGroundColor Yellow
}
}
</style>
Project starts 2023-12-01
projectscale monthly
-- WP1 Project Management --
[M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 80% completed
[M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed
-- WP2 Vertical Hosting --
[D2.5 Technical architecture document] starts 2024-01-01 and ends 2024-03-29 and is 60% completed
[D2.7 Analyze investment on fediverse] starts 2023-12-01 and ends 2024-04-30 and is colored in Red
[D2.6 CI/CD setup] starts 2024-03-01 and ends 2024-10-31 and is colored in Red
[D2.4 Nix Packages and NixOS Services] starts 2024-05-01 and ends 2024-11-29 and is colored in Red
[D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29 and is 80% completed
[D2.2 Software Release beta environment] starts 2025-01-01 and ends 2025-12-31 and is 0% completed
[D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed
-- WP3 Vertical Public organizations --
[D3.1 Requirements document] as [c1] starts 2023-12-01 and ends 2024-07-31 and is colored in Red
[D3.2 Pilot program proposals] starts at [c1]'s end and ends 2024-11-29 and is colored in Red
[D3.3 Technical architecture document pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed
[D3.4 Nix service flakes, packages and services for pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed
[D3.5 CI/CD setup for pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts 2025-05-01 and ends 2026-10-30 and is 0% completed
-- WP4 Open calls and grant management --
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed
[M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed
[M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed
[D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
-- WP5 Enhancement and Usability --
[D5.6 Setup UX design testlab] starts 2023-12-01 and ends 2024-07-31 and is colored in Red
[D5.1 User requirement document] starts 2024-05-01 and ends 2024-08-30 and is colored in Red
[D5.2 UX design] starts 2024-09-02 and ends 2025-11-28 and is 0% completed
[D5.3 UX design implementation] starts 2025-12-01 and ends 2026-05-29 and is 0% completed
[D5.4 UX design user studies] starts 2026-05-01 and ends 2026-09-30 and is 0% completed
[D5.5 Design iteration and final release] starts 2026-10-01 and ends 2026-11-30 and is 0% completed
-- WP6 Outreach and Dissemination --
[D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red
[D6.2 Media package] starts 2024-05-01 and ends 2024-07-31 and is colored in Red
[D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed
[D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
@endgantt