Commit graph

2 commits

Author SHA1 Message Date
gheorghe ad0b6aa093 Update planning/gantt.puml
Having it in red means nothing was worked on for this deliverable, which is not the reality. This is why I updated the status of the D2.1 Software release test environment to 80% completed and the task in progress. I considered today's situation, the missing architecture document, the grant agreement specifications for this deliverable and work package, and the demo that has already been presented. We'll add the remaining 20% after the architecture document is finished.
2024-11-21 16:25:34 +01:00
Ronny Lam b955e054d5 renamed .uml to .puml 2024-11-21 11:17:13 +01:00
Renamed from planning/gantt.uml (Browse further)