	Update planning/gantt.puml
Having it in red means nothing was worked on for this deliverable, which is not the reality. This is why I updated the status of the D2.1 Software release test environment to 80% completed and the task in progress. I considered today's situation, the missing architecture document, the grant agreement specifications for this deliverable and work package, and the demo that has already been presented. We'll add the remaining 20% after the architecture document is finished.
This commit is contained in:
		
							parent
							
								
									b9421f7339
								
							
						
					
					
						commit
						48237e1863
					
				
					 1 changed files with 1 additions and 1 deletions
				
			
		|  | @ -25,7 +25,7 @@ projectscale monthly | |||
| [D2.7 Analyze investment on fediverse] starts 2023-12-01 and ends 2024-04-30 and is colored in Red | ||||
| [D2.6 CI/CD setup] starts 2024-03-01 and ends 2024-10-31 and is colored in Red | ||||
| [D2.4 Nix Packages and NixOS Services] starts 2024-05-01 and ends 2024-11-29 and is colored in Red | ||||
| [D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29 and is colored in Red | ||||
| [D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29  and is 80% completed | ||||
| [D2.2 Software Release beta environment] starts 2025-01-01 and ends 2025-12-31 and is 0% completed | ||||
| [D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
|  |  | |||