| @startgantt
 | |
| skinparam backgroundcolor transparent
 | |
| 
 | |
| <style>
 | |
| ganttDiagram {
 | |
|   task {
 | |
|     BackGroundColor GreenYellow
 | |
|     LineColor Green 
 | |
|   }
 | |
|   undone {
 | |
|     BackGroundColor Yellow
 | |
|   }
 | |
| }
 | |
| </style>
 | |
| 
 | |
| 2024-12-20 to 2025-01-05 is closed
 | |
| 2025-07-01 to 2025-08-31 is closed
 | |
| Project starts 2023-12-01
 | |
| projectscale monthly
 | |
| 'Separator just at 2025-05-31
 | |
| [Reporting period 1] happens at 2025-05-31
 | |
| Separator just at [Reporting period 1]'s end
 | |
| -- WP1 Project Management --
 | |
| [M1 First ActivityPub presence] as [a1] starts 2023-12-29 and requires 7 days and is 100% completed
 | |
| [D1.1 Data Management Plan] as [a11] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
 | |
| [M6 First Tech talk] as [a6] starts 2024-05-31 and requires 7 days and is 100% completed
 | |
| [M7 First Workshop] as [a7] starts 2024-07-31 and requires 7 days and is 100% completed
 | |
| 
 | |
| -- WP2 Vertical Hosting --
 | |
| [D2.5 Technical architecture document] as [b5] starts 2024-01-01 and ends 2025-06-15 and is 90% completed
 | |
| ' [b5] is colored in Red
 | |
| [D2.1 Implementation] as [b1] starts 2024-03-01 and ends 2026-11-30 and is 50% completed
 | |
| [D2.2 Produce sample applications] as [b2] starts 2024-05-01 and ends 2026-11-30 and is 50% completed
 | |
| 
 | |
| -- WP3 Vertical Public organizations --
 | |
| [D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 100% completed
 | |
| [c1] is colored in Grey
 | |
| [D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 100% completed
 | |
| [c2] is colored in Grey
 | |
| [D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
 | |
| [c3] is colored in Grey
 | |
| [D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
 | |
| [c4] is colored in Grey
 | |
| [D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
 | |
| [c5] is colored in Grey
 | |
| [D3.6 Running Fediverse software for public organisations advisory] as [c6] starts at [c3]'s end and ends 2025-06-15 and is 100% completed
 | |
| [c6] is colored in Grey
 | |
| 
 | |
| -- WP4 Open calls and grant management --
 | |
| [M2 Announcement open call] as [d2] starts 2023-12-29 and requires 7 days and is 100% completed
 | |
| [M3 First open call opens] as [d3] starts 2024-02-01 and requires 7 days and is 100% completed
 | |
| [M4 First batch of grantees selected] as [d4] starts 2024-03-29 and requires 7 days and is 100% completed
 | |
| [D4.1 Overview of granted projects] as [d41] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
 | |
| 
 | |
| -- WP5 Enhancement and Usability --
 | |
| [D5.6 Setup UX design testlab] as [e6] starts 2023-12-01 and ends 2024-07-31 and is 100% completed
 | |
| [D5.1 User requirement document] as [e1] starts 2024-05-01 and ends 2024-08-30 and is 100% completed
 | |
| [D5.2 UX design] as [e2] starts 2024-09-02 and ends 2025-11-28 and is 100% completed
 | |
| [D5.3 UX design implementation] as [e3] starts 2025-12-01 and ends 2026-05-29 and is 100% completed
 | |
| [e3] is colored in Grey
 | |
| [D5.4 UX design user studies] as [e4] starts 2026-05-01 and ends 2026-09-30 and is 100% completed
 | |
| [e4] is colored in Grey
 | |
| [D5.5 Design iteration and final release] as [e5] starts 2026-05-01 and ends 2026-11-30 and is 100% completed
 | |
| [e5] is colored in Grey
 | |
| 
 | |
| -- WP6 Outreach and Dissemination --
 | |
| [D6.1 Communication strategy] as [f1] starts 2023-12-01 and ends 2024-01-31 and is 100% completed
 | |
| [D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 100% completed
 | |
| [D6.3 Communication report first period] as [f3] starts 2025-03-03 and ends 2025-04-30 and is 100% completed
 | |
| [D6.4 Communication report second period] as [f4] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
 | |
| [D6.5 Developer outreach] as [f5] starts 2025-01-01 and ends 2026-11-30 and is 10% completed
 | |
| @endgantt
 |