|  | @ -13,32 +13,69 @@ ganttDiagram { | |||
| } | ||||
| </style> | ||||
| 
 | ||||
| 2024-12-20 to 2025-01-05 is closed | ||||
| 2025-07-01 to 2025-08-31 is closed | ||||
| Project starts 2023-12-01 | ||||
| projectscale monthly | ||||
| 
 | ||||
| 'Separator just at 2025-05-31 | ||||
| [Reporting period 1] happens at 2025-05-31 | ||||
| Separator just at [Reporting period 1]'s end | ||||
| -- WP1 Project Management -- | ||||
| [D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed | ||||
| [M1 First ActivityPub presence] as [a1] starts 2023-12-29 and requires 7 days and is 100% completed | ||||
| [D1.1 Data Management Plan] as [a11] starts 2023-12-01 and ends 2024-02-29 and is 100% completed | ||||
| [M6 First Tech talk] as [a6] starts 2024-05-31 and requires 7 days and is 100% completed | ||||
| [M7 First Workshop] as [a7] starts 2024-07-31 and requires 7 days and is 100% completed | ||||
| 
 | ||||
| -- WP2 Implementation -- | ||||
| [D2.1 software release 1.0] starts 2025-01-01 and ends 2025-12-31 and is 30% completed | ||||
| [D2.2 kick-start internal feedback cycle] starts 2025-08-01 and ends 2025-12-31 and is 0% completed | ||||
| -- WP2 Vertical Hosting -- | ||||
| [D2.5 Technical architecture document] as [b5] starts 2024-01-01 and ends 2025-06-15 and is 90% completed | ||||
| ' [b5] is colored in Red | ||||
| [D2.7 Analyze investment on fediverse] as [b7] starts 2023-12-01 and ends 2024-04-30 | ||||
| [D2.6 CI/CD setup] as [b6] starts 2024-03-01 and ends 2025-11-31 and is 40% completed | ||||
| ' [b6] is colored in Red | ||||
| [D2.4 Nix Packages and NixOS Services] as [b4] starts 2024-05-01 and ends 2024-11-29 and is 67% completed | ||||
| [D2.1 Software Release test environment] as [b1] starts 2024-06-28 and ends 2025-03-31 and is 100% completed | ||||
| [D2.2 Software Release beta environment] as [b2] starts 2025-01-01 and ends 2025-12-31 and is 50% completed | ||||
| ' [b2] is colored in Red | ||||
| [D2.3 Software release 1.0] as [b3] starts 2025-12-01 and ends 2025-12-31 and is 0% completed | ||||
| [D2.8 Software integrated with hosting provider] as [b8] starts 2025-12-01 and ends 2026-04-30 and is 0% completed | ||||
| [D2.9 Security check] as [b9] starts 2026-04-01 and ends 2026-04-30 and is 0% completed | ||||
| 
 | ||||
| -- WP3 Dissemination -- | ||||
| [D3.1 automated dev-ops workflows] starts 2025-01-01 and ends 2025-11-31 and is 20% completed | ||||
| [D3.2 empower developers] starts 2026-01-01 and ends 2026-04-30 and is 10% completed | ||||
| [D3.3 community engagement] starts 2026-03-01 and ends 2026-11-30 and is 20% completed | ||||
| -- WP3 Vertical Public organizations -- | ||||
| [D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 100% completed | ||||
| [c1] is colored in Grey | ||||
| [D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 100% completed | ||||
| [c2] is colored in Grey | ||||
| [D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 100% completed | ||||
| [c3] is colored in Grey | ||||
| [D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 100% completed | ||||
| [c4] is colored in Grey | ||||
| [D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 100% completed | ||||
| [c5] is colored in Grey | ||||
| [D3.6 Running Fediverse software for public organisations advisory] as [c6] starts at [c3]'s end and ends 2025-06-15 and is 100% completed | ||||
| [c6] is colored in Grey | ||||
| 
 | ||||
| -- WP4 Exploitation: Vertical Hosting -- | ||||
| [D4.1 software integrated with hosting provider] starts 2025-12-01 and ends 2026-04-30 and is 0% completed | ||||
| [D4.2 security audit] starts 2026-04-01 and ends 2026-04-30 and is 0% completed | ||||
| -- WP4 Open calls and grant management -- | ||||
| [M2 Announcement open call] as [d2] starts 2023-12-29 and requires 7 days and is 100% completed | ||||
| [M3 First open call opens] as [d3] starts 2024-02-01 and requires 7 days and is 100% completed | ||||
| [M4 First batch of grantees selected] as [d4] starts 2024-03-29 and requires 7 days and is 100% completed | ||||
| [D4.1 Overview of granted projects] as [d41] starts 2026-07-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
| -- WP5 Exploitation: Enhancement and Usability -- | ||||
| [D5.1 round out user experience] starts 2026-05-01 and ends 2026-10-30  and is 0% completed | ||||
| [D5.2 complete application offering] starts 2026-07-01 and ends 2026-11-30 and is 0% completed | ||||
| -- WP5 Enhancement and Usability -- | ||||
| [D5.6 Setup UX design testlab] as [e6] starts 2023-12-01 and ends 2024-07-31 and is 100% completed | ||||
| [D5.1 User requirement document] as [e1] starts 2024-05-01 and ends 2024-08-30 and is 100% completed | ||||
| [D5.2 UX design] as [e2] starts 2024-09-02 and ends 2025-11-28 and is 100% completed | ||||
| [e2] is colored in Grey | ||||
| [D5.3 UX design implementation] as [e3] starts 2025-12-01 and ends 2026-05-29 and is 100% completed | ||||
| [e3] is colored in Grey | ||||
| [D5.4 UX design user studies] as [e4] starts 2026-05-01 and ends 2026-09-30 and is 100% completed | ||||
| [e4] is colored in Grey | ||||
| [D5.5 Design iteration and final release] as [e5] starts 2026-05-01 and ends 2026-10-30 and is 0% completed | ||||
| [D5.7 Complete application offering] as [e7] starts 2026-07-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
| -- WP6 Open calls and grant management -- | ||||
| [M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed | ||||
| [M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed | ||||
| [M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed | ||||
| [D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed | ||||
| -- WP6 Outreach and Dissemination -- | ||||
| [D6.1 Communication strategy] as [f1] starts 2023-12-01 and ends 2024-01-31 and is 100% completed | ||||
| [D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 100% completed | ||||
| [D6.3 Communication report first period] as [f3] starts 2025-03-03 and ends 2025-04-30 and is 100% completed | ||||
| [D6.4 Communication report second period] as [f4] starts 2026-09-01 and ends 2026-10-30 and is 0% completed | ||||
| [D6.5 Empower developers] as [f5] starts 2026-01-01 and ends 2026-04-30 and is 10% completed | ||||
| @endgantt | ||||
|  |  | |||
|  | @ -3,13 +3,11 @@ title: Fediversity work package interdependencies | |||
| --- | ||||
| flowchart | ||||
|     management["WP1: Project Management"] | ||||
|     implementation["WP2: Implementation"] | ||||
|     vertical["WP3: Vertical Hosting"] | ||||
|     ux["WP4: Enhancement & Usability"] | ||||
|     dissemination["WP5: Dissemination & Outreach"] | ||||
|     grants["WP6: Open calls and grant management"] | ||||
|     vertical["WP2: Vertical Hosting"] | ||||
|     grants["WP4: Open calls and grant management"] | ||||
|     ux["WP5: Enhancement & Usability"] | ||||
|     dissemination["WP6: Outreach & Dissemination"] | ||||
| 
 | ||||
|     management --> implementation & vertical & ux & dissemination & grants | ||||
|     implementation --> vertical & ux | ||||
|     management --> vertical & ux & dissemination & grants | ||||
|     vertical --> ux | ||||
|     implementation & vertical & ux & dissemination --> grants | ||||
|     vertical & ux & dissemination --> grants | ||||
|  |  | |||
										