initial gantt chart for proposal rewrite
This commit is contained in:
		
							parent
							
								
									7b828b497d
								
							
						
					
					
						commit
						80bc7e33e3
					
				
					 2 changed files with 18 additions and 41 deletions
				
			
		
										
											Binary file not shown.
										
									
								
							| Before Width: | Height: | Size: 95 KiB After Width: | Height: | Size: 44 KiB | 
|  | @ -1,4 +1,5 @@ | |||
| @startgantt | ||||
| skinparam backgroundcolor transparent | ||||
| 
 | ||||
| <style> | ||||
| ganttDiagram { | ||||
|  | @ -12,55 +13,31 @@ ganttDiagram { | |||
| } | ||||
| </style> | ||||
| 
 | ||||
| 2024-12-20 to  2025-01-5 is closed | ||||
| 2025-07-01 to 2025-08-31 is closed | ||||
| Project starts 2023-12-01 | ||||
| projectscale monthly | ||||
| 'Separator just at 2025-05-31 | ||||
| [Reporting period 1] happens at 2025-05-31 | ||||
| Separator just at [Reporting period 1]'s end | ||||
| 
 | ||||
| -- WP1 Project Management -- | ||||
| [M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed | ||||
| [D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 100% completed | ||||
| [M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed | ||||
| [M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed | ||||
| [D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed | ||||
| 
 | ||||
| -- WP2 Vertical Hosting -- | ||||
| [D2.5 Technical architecture document] starts 2024-01-01 and ends 2024-03-29 and is 60% completed | ||||
| [D2.7 Analyze investment on fediverse] starts 2023-12-01 and ends 2024-04-30 and is colored in Red | ||||
| [D2.6 CI/CD setup] starts 2024-03-01 and ends 2024-10-31 and is colored in Red | ||||
| [D2.4 Nix Packages and NixOS Services] starts 2024-05-01 and ends 2024-11-29 and is 67% completed | ||||
| [D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29 and is 67% completed | ||||
| [D2.2 Software Release beta environment] starts 2025-01-01 and ends 2025-12-31 and is 0% completed | ||||
| [D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed | ||||
| -- WP2 Implementation -- | ||||
| [D2.1 software release 1.0] starts 2025-01-01 and ends 2025-12-31 and is 30% completed | ||||
| [D2.2 kick-start internal feedback cycle] starts 2025-08-01 and ends 2025-12-31 and is 0% completed | ||||
| 
 | ||||
| -- WP3 Vertical Public organizations -- | ||||
| [D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 0% completed | ||||
| [D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 0% completed | ||||
| [D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 0% completed | ||||
| [D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 0% completed | ||||
| [D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 0% completed | ||||
| [D3.6 Running Fediverse software for public organisations advisory] starts at [c3]'s end and ends 2026-10-30 and is 0% completed | ||||
| [D3.6 Running Fediverse software for public organisations advisory] starts at [c4]'s end and ends 2026-10-30 and is 0% completed | ||||
| [D3.6 Running Fediverse software for public organisations advisory] starts at [c5]'s end and ends 2026-10-30 and is 0% completed | ||||
| -- WP3 Dissemination -- | ||||
| [D3.1 automated dev-ops workflows] starts 2025-01-01 and ends 2025-11-31 and is 20% completed | ||||
| [D3.2 empower developers] starts 2026-01-01 and ends 2026-04-30 and is 10% completed | ||||
| [D3.3 community engagement] starts 2026-03-01 and ends 2026-11-30 and is 20% completed | ||||
| 
 | ||||
| -- WP4 Open calls and grant management -- | ||||
| -- WP4 Exploitation: Vertical Hosting -- | ||||
| [D4.1 software integrated with hosting provider] starts 2025-12-01 and ends 2026-04-30 and is 0% completed | ||||
| 
 | ||||
| -- WP5 Exploitation: Enhancement and Usability -- | ||||
| [D5.1 round out user experience] starts 2026-05-01 and ends 2026-11-30 and is 0% completed | ||||
| [D5.2 complete application offering] starts 2026-05-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
| -- WP6 Open calls and grant management -- | ||||
| [M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed | ||||
| [M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed | ||||
| [M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed | ||||
| [D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
| -- WP5 Enhancement and Usability -- | ||||
| [D5.6 Setup UX design testlab] starts 2023-12-01 and ends 2024-07-31 and is colored in Red | ||||
| [D5.1 User requirement document] starts 2024-05-01 and ends 2024-08-30 and is colored in Red | ||||
| [D5.2 UX design] starts 2024-09-02 and ends 2025-11-28 and is 0% completed | ||||
| [D5.3 UX design implementation] starts 2025-12-01 and ends 2026-05-29 and is 0% completed | ||||
| [D5.4 UX design user studies] starts 2026-05-01 and ends 2026-09-30 and is 0% completed | ||||
| [D5.5 Design iteration and final release] starts 2026-10-01 and ends 2026-11-30 and is 0% completed | ||||
| 
 | ||||
| -- WP6 Outreach and Dissemination -- | ||||
| [D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red | ||||
| [D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 0% completed | ||||
| [D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed | ||||
| [D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed | ||||
| @endgantt | ||||
|  |  | |||