meta/planning/gantt.puml

43 lines
1.6 KiB
Text

@startgantt
skinparam backgroundcolor transparent
<style>
ganttDiagram {
task {
BackGroundColor GreenYellow
LineColor Green
}
undone {
BackGroundColor Yellow
}
}
</style>
Project starts 2023-12-01
projectscale monthly
-- WP1 Project Management --
[D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed
-- WP2 Implementation --
[D2.1 software release 1.0] starts 2025-01-01 and ends 2025-12-31 and is 30% completed
[D2.2 kick-start internal feedback cycle] starts 2025-08-01 and ends 2025-12-31 and is 0% completed
-- WP3 Dissemination --
[D3.1 automated dev-ops workflows] starts 2025-01-01 and ends 2025-11-31 and is 20% completed
[D3.2 empower developers] starts 2026-01-01 and ends 2026-04-30 and is 10% completed
[D3.3 community engagement] starts 2026-03-01 and ends 2026-11-30 and is 20% completed
-- WP4 Exploitation: Vertical Hosting --
[D4.1 software integrated with hosting provider] starts 2025-12-01 and ends 2026-04-30 and is 0% completed
-- WP5 Exploitation: Enhancement and Usability --
[D5.1 round out user experience] starts 2026-05-01 and ends 2026-11-30 and is 0% completed
[D5.2 complete application offering] starts 2026-05-01 and ends 2026-11-30 and is 0% completed
-- WP6 Open calls and grant management --
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed
[M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed
[M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed
[D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
@endgantt