initial gantt chart for proposal rewrite #33

Merged
kiara merged 8 commits from proposal-gantt into main 2025-06-12 17:23:38 +02:00
4 changed files with 53 additions and 34 deletions

Binary file not shown.

Before

Width:  |  Height:  |  Size: 95 KiB

After

Width:  |  Height:  |  Size: 82 KiB

View file

@ -1,4 +1,5 @@
@startgantt @startgantt
skinparam backgroundcolor transparent
<style> <style>
ganttDiagram { ganttDiagram {
@ -12,7 +13,7 @@ ganttDiagram {
} }
</style> </style>
2024-12-20 to 2025-01-5 is closed 2024-12-20 to 2025-01-05 is closed
2025-07-01 to 2025-08-31 is closed 2025-07-01 to 2025-08-31 is closed
Project starts 2023-12-01 Project starts 2023-12-01
projectscale monthly projectscale monthly
@ -20,47 +21,52 @@ projectscale monthly
[Reporting period 1] happens at 2025-05-31 [Reporting period 1] happens at 2025-05-31
Separator just at [Reporting period 1]'s end Separator just at [Reporting period 1]'s end
-- WP1 Project Management -- -- WP1 Project Management --
[M1 First ActivityPub presence] starts 2023-12-29 and requires 7 days and is 100% completed [M1 First ActivityPub presence] as [a1] starts 2023-12-29 and requires 7 days and is 100% completed
[D1.1 Data Management Plan] starts 2023-12-01 and ends 2024-02-29 and is 100% completed [D1.1 Data Management Plan] as [a11] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
[M6 First Tech talk] starts 2024-05-31 and requires 7 days and is 100% completed [M6 First Tech talk] as [a6] starts 2024-05-31 and requires 7 days and is 100% completed
[M7 First Workshop] starts 2024-07-31 and requires 7 days and is 100% completed [M7 First Workshop] as [a7] starts 2024-07-31 and requires 7 days and is 100% completed
kiara marked this conversation as resolved Outdated

I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing

I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing
-- WP2 Vertical Hosting -- -- WP2 Vertical Hosting --
kiara marked this conversation as resolved Outdated

We can rename the workpackage I guess, but we can't remove past items since they have been done.

We can rename the workpackage I guess, but we can't remove past items since they have been done.

Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers

Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers
[D2.5 Technical architecture document] starts 2024-01-01 and ends 2024-03-29 and is 60% completed [D2.5 Technical architecture document] as [b5] starts 2024-01-01 and ends 2025-06-15 and is 90% completed
[D2.7 Analyze investment on fediverse] starts 2023-12-01 and ends 2024-04-30 and is colored in Red ' [b5] is colored in Red
[D2.6 CI/CD setup] starts 2024-03-01 and ends 2024-10-31 and is colored in Red [D2.1 Implementation] as [b1] starts 2024-03-01 and ends 2026-11-30 and is 50% completed
[D2.4 Nix Packages and NixOS Services] starts 2024-05-01 and ends 2024-11-29 and is 67% completed [D2.2 Produce sample applications] as [b2] starts 2024-05-01 and ends 2026-11-30 and is 50% completed
[D2.1 Software Release test environment] starts 2024-06-28 and ends 2024-11-29 and is 67% completed
[D2.2 Software Release beta environment] starts 2025-01-01 and ends 2025-12-31 and is 0% completed
[D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed
-- WP3 Vertical Public organizations -- -- WP3 Vertical Public organizations --
[D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 0% completed [D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 100% completed
[D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 0% completed [c1] is colored in Grey
[D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 0% completed [D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 100% completed
[D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 0% completed [c2] is colored in Grey
[D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 0% completed [D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c3]'s end and ends 2026-10-30 and is 0% completed [c3] is colored in Grey
[D3.6 Running Fediverse software for public organisations advisory] starts at [c4]'s end and ends 2026-10-30 and is 0% completed [D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c5]'s end and ends 2026-10-30 and is 0% completed [c4] is colored in Grey
[D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
[c5] is colored in Grey
[D3.6 Running Fediverse software for public organisations advisory] as [c6] starts at [c3]'s end and ends 2025-06-15 and is 100% completed
[c6] is colored in Grey
-- WP4 Open calls and grant management -- -- WP4 Open calls and grant management --
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed [M2 Announcement open call] as [d2] starts 2023-12-29 and requires 7 days and is 100% completed
[M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed [M3 First open call opens] as [d3] starts 2024-02-01 and requires 7 days and is 100% completed
[M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed [M4 First batch of grantees selected] as [d4] starts 2024-03-29 and requires 7 days and is 100% completed
[D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed [D4.1 Overview of granted projects] as [d41] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
-- WP5 Enhancement and Usability -- -- WP5 Enhancement and Usability --
[D5.6 Setup UX design testlab] starts 2023-12-01 and ends 2024-07-31 and is colored in Red [D5.6 Setup UX design testlab] as [e6] starts 2023-12-01 and ends 2024-07-31 and is 100% completed
[D5.1 User requirement document] starts 2024-05-01 and ends 2024-08-30 and is colored in Red [D5.1 User requirement document] as [e1] starts 2024-05-01 and ends 2024-08-30 and is 100% completed
[D5.2 UX design] starts 2024-09-02 and ends 2025-11-28 and is 0% completed [D5.2 UX design] as [e2] starts 2024-09-02 and ends 2025-11-28 and is 100% completed
[D5.3 UX design implementation] starts 2025-12-01 and ends 2026-05-29 and is 0% completed [D5.3 UX design implementation] as [e3] starts 2025-12-01 and ends 2026-05-29 and is 100% completed
[D5.4 UX design user studies] starts 2026-05-01 and ends 2026-09-30 and is 0% completed [e3] is colored in Grey
[D5.5 Design iteration and final release] starts 2026-10-01 and ends 2026-11-30 and is 0% completed [D5.4 UX design user studies] as [e4] starts 2026-05-01 and ends 2026-09-30 and is 100% completed
[e4] is colored in Grey
[D5.5 Design iteration and final release] as [e5] starts 2026-05-01 and ends 2026-11-30 and is 100% completed
[e5] is colored in Grey
-- WP6 Outreach and Dissemination -- -- WP6 Outreach and Dissemination --
[D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red [D6.1 Communication strategy] as [f1] starts 2023-12-01 and ends 2024-01-31 and is 100% completed
[D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 0% completed [D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 100% completed
[D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed [D6.3 Communication report first period] as [f3] starts 2025-03-03 and ends 2025-04-30 and is 100% completed
[D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed [D6.4 Communication report second period] as [f4] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
[D6.5 Developer outreach] as [f5] starts 2025-01-01 and ends 2026-11-30 and is 10% completed
@endgantt @endgantt

View file

@ -0,0 +1,13 @@
---
title: Fediversity work package interdependencies
---
flowchart
management["WP1: Project Management"]
vertical["WP2: Vertical Hosting"]
grants["WP4: Open calls and grant management"]
ux["WP5: Enhancement & Usability"]
dissemination["WP6: Outreach & Dissemination"]
management --> vertical & ux & dissemination & grants
vertical --> ux
vertical & ux & dissemination --> grants