2024-12-20 to 2025-01-05 is closed
|
||||
2025-07-01 to 2025-08-31 is closed
|
||||
Project starts 2023-12-01
|
||||
projectscale monthly
|
||||
|
||||
'Separator just at 2025-05-31
|
||||
[Reporting period 1] happens at 2025-05-31
|
||||
Separator just at [Reporting period 1]'s end
|
||||
-- WP1 Project Management --
|
||||
[D1.1 technical architecture document] starts 2025-05-15 and ends 2024-06-15 and is 80% completed
|
||||
[M1 First ActivityPub presence] as [a1] starts 2023-12-29 and requires 7 days and is 100% completed
|
||||
[D1.1 Data Management Plan] as [a11] starts 2023-12-01 and ends 2024-02-29 and is 100% completed
|
||||
[M6 First Tech talk] as [a6] starts 2024-05-31 and requires 7 days and is 100% completed
|
||||
[M7 First Workshop] as [a7] starts 2024-07-31 and requires 7 days and is 100% completed
|
||||
|
||||
-- WP2 Implementation --
|
||||
[D2.1 software release 1.0] starts 2025-01-01 and ends 2025-12-31 and is 30% completed
|
||||
[D2.2 kick-start internal feedback cycle] starts 2025-08-01 and ends 2025-12-31 and is 0% completed
|
||||
-- WP2 Vertical Hosting --
|
||||
[D2.5 Technical architecture document] as [b5] starts 2024-01-01 and ends 2025-06-15 and is 90% completed
|
||||
' [b5] is colored in Red
|
||||
[D2.7 Analyze investment on fediverse] as [b7] starts 2023-12-01 and ends 2024-04-30
|
||||
[D2.6 CI/CD setup] as [b6] starts 2024-03-01 and ends 2025-11-31 and is 40% completed
|
||||
' [b6] is colored in Red
|
||||
[D2.4 Nix Packages and NixOS Services] as [b4] starts 2024-05-01 and ends 2024-11-29 and is 67% completed
|
||||
[D2.1 Software Release test environment] as [b1] starts 2024-06-28 and ends 2025-03-31 and is 100% completed
|
||||
[D2.2 Software Release beta environment] as [b2] starts 2025-01-01 and ends 2025-12-31 and is 50% completed
|
||||
' [b2] is colored in Red
|
||||
[D2.3 Software release 1.0] as [b3] starts 2025-12-01 and ends 2025-12-31 and is 0% completed
|
||||
[D2.8 Software integrated with hosting provider] as [b8] starts 2025-12-01 and ends 2026-04-30 and is 0% completed
|
||||
[D2.9 Security check] as [b9] starts 2026-04-01 and ends 2026-04-30 and is 0% completed
|
||||
|
||||
-- WP3 Dissemination --
|
||||
kiara marked this conversation as resolved
Outdated
|
||||
[D3.1 automated dev-ops workflows] starts 2025-01-01 and ends 2025-11-31 and is 20% completed
|
||||
[D3.2 empower developers] starts 2026-01-01 and ends 2026-04-30 and is 10% completed
|
||||
kiara marked this conversation as resolved
Outdated
fricklerhandwerk
commented
We can rename the workpackage I guess, but we can't remove past items since they have been done. We can rename the workpackage I guess, but we can't remove past items since they have been done.
fricklerhandwerk
commented
Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers Also renaming existing items is really confusing, we we want things changed just add new deliverable identifiers
|
||||
[D3.3 community engagement] starts 2026-03-01 and ends 2026-11-30 and is 20% completed
|
||||
-- WP3 Vertical Public organizations --
|
||||
[D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 100% completed
|
||||
[c1] is colored in Grey
|
||||
[D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 100% completed
|
||||
[c2] is colored in Grey
|
||||
[D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
|
||||
[c3] is colored in Grey
|
||||
[D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
|
||||
[c4] is colored in Grey
|
||||
[D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 100% completed
|
||||
[c5] is colored in Grey
|
||||
[D3.6 Running Fediverse software for public organisations advisory] as [c6] starts at [c3]'s end and ends 2025-06-15 and is 100% completed
|
||||
[c6] is colored in Grey
|
||||
|
||||
-- WP4 Exploitation: Vertical Hosting --
|
||||
[D4.1 software integrated with hosting provider] starts 2025-12-01 and ends 2026-04-30 and is 0% completed
|
||||
[D4.2 security audit] starts 2026-04-01 and ends 2026-04-30 and is 0% completed
|
||||
-- WP4 Open calls and grant management --
|
||||
[M2 Announcement open call] as [d2] starts 2023-12-29 and requires 7 days and is 100% completed
|
||||
[M3 First open call opens] as [d3] starts 2024-02-01 and requires 7 days and is 100% completed
|
||||
[M4 First batch of grantees selected] as [d4] starts 2024-03-29 and requires 7 days and is 100% completed
|
||||
[D4.1 Overview of granted projects] as [d41] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
|
||||
|
||||
-- WP5 Exploitation: Enhancement and Usability --
|
||||
[D5.1 round out user experience] starts 2026-05-01 and ends 2026-10-30 and is 0% completed
|
||||
[D5.2 complete application offering] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
|
||||
-- WP5 Enhancement and Usability --
|
||||
[D5.6 Setup UX design testlab] as [e6] starts 2023-12-01 and ends 2024-07-31 and is 100% completed
|
||||
[D5.1 User requirement document] as [e1] starts 2024-05-01 and ends 2024-08-30 and is 100% completed
|
||||
[D5.2 UX design] as [e2] starts 2024-09-02 and ends 2025-11-28 and is 100% completed
|
||||
[e2] is colored in Grey
|
||||
[D5.3 UX design implementation] as [e3] starts 2025-12-01 and ends 2026-05-29 and is 100% completed
|
||||
[e3] is colored in Grey
|
||||
[D5.4 UX design user studies] as [e4] starts 2026-05-01 and ends 2026-09-30 and is 100% completed
|
||||
[e4] is colored in Grey
|
||||
[D5.5 Design iteration and final release] as [e5] starts 2026-05-01 and ends 2026-10-30 and is 0% completed
|
||||
[D5.7 Complete application offering] as [e7] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
|
||||
|
||||
-- WP6 Open calls and grant management --
|
||||
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed
|
||||
[M3 First open call opens] starts 2024-02-01 and requires 7 days and is 100% completed
|
||||
[M4 First batch of grantees selected] starts 2024-03-29 and requires 7 days and is 0% completed
|
||||
[D4.1 Overview of granted projects] starts 2026-07-01 and ends 2026-11-30 and is 0% completed
|
||||
-- WP6 Outreach and Dissemination --
|
||||
[D6.1 Communication strategy] as [f1] starts 2023-12-01 and ends 2024-01-31 and is 100% completed
|
||||
[D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 100% completed
|
||||
[D6.3 Communication report first period] as [f3] starts 2025-03-03 and ends 2025-04-30 and is 100% completed
|
||||
[D6.4 Communication report second period] as [f4] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
|
||||
[D6.5 Empower developers] as [f5] starts 2026-01-01 and ends 2026-04-30 and is 10% completed
|
||||
@endgantt
|
||||
|
|
|
@ -3,13 +3,11 @@ title: Fediversity work package interdependencies
|
|||
---
|
||||
flowchart
|
||||
management["WP1: Project Management"]
|
||||
implementation["WP2: Implementation"]
|
||||
vertical["WP3: Vertical Hosting"]
|
||||
ux["WP4: Enhancement & Usability"]
|
||||
dissemination["WP5: Dissemination & Outreach"]
|
||||
grants["WP6: Open calls and grant management"]
|
||||
vertical["WP2: Vertical Hosting"]
|
||||
grants["WP4: Open calls and grant management"]
|
||||
ux["WP5: Enhancement & Usability"]
|
||||
dissemination["WP6: Outreach & Dissemination"]
|
||||
|
||||
management --> implementation & vertical & ux & dissemination & grants
|
||||
implementation --> vertical & ux
|
||||
management --> vertical & ux & dissemination & grants
|
||||
vertical --> ux
|
||||
implementation & vertical & ux & dissemination --> grants
|
||||
vertical & ux & dissemination --> grants
|
||||
|
|
Binary file not shown.
After Width: | Height: | Size: 43 KiB |
Loading…
Add table
Reference in a new issue
I don't think we can remove the publicity things, also they've been done and keep getting done so it's worth showing