gheorghe ad0b6aa093 Update planning/gantt.puml
Having it in red means nothing was worked on for this deliverable, which is not the reality. This is why I updated the status of the D2.1 Software release test environment to 80% completed and the task in progress. I considered today's situation, the missing architecture document, the grant agreement specifications for this deliverable and work package, and the demo that has already been presented. We'll add the remaining 20% after the architecture document is finished.
2024-11-21 16:25:34 +01:00
Ronny Lam b955e054d5 renamed .uml to .puml 2024-11-21 11:17:13 +01:00
Ronny Lam 89dc0c0eef converted to uml and changes after meeting 2024-11-21 09:09:14 +01:00
Ronny Lam 2f6c98ad4a changed some states in gantt 2024-11-14 13:11:55 +01:00
Ronny Lam ee32e35d0a add gantt image 2024-11-13 16:33:09 +01:00
Ronny Lam 49efc013d2 moved gantt chart 2024-11-13 16:29:38 +01:00