update gantt according to pm meeting

This commit is contained in:
Ronny Lam 2024-12-05 17:35:22 +01:00
parent f7cb153e55
commit 4f5e5dab0c
2 changed files with 11 additions and 7 deletions

Binary file not shown.

Before

Width:  |  Height:  |  Size: 80 KiB

After

Width:  |  Height:  |  Size: 91 KiB

View file

@ -12,6 +12,7 @@ ganttDiagram {
} }
</style> </style>
2024-12-20 to 2025-01-5 is closed
Project starts 2023-12-01 Project starts 2023-12-01
projectscale monthly projectscale monthly
-- WP1 Project Management -- -- WP1 Project Management --
@ -30,12 +31,15 @@ projectscale monthly
[D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed [D2.3 Software release 1.0] starts 2025-12-01 and ends 2026-11-30 and is 0% completed
-- WP3 Vertical Public organizations -- -- WP3 Vertical Public organizations --
[D3.1 Requirements document] as [c1] starts 2023-12-01 and ends 2024-07-31 and is colored in Red 2025-07-01 to 2025-08-31 is closed
[D3.2 Pilot program proposals] starts at [c1]'s end and ends 2024-11-29 and is colored in Red [D3.1 Requirements document] as [c1] starts 2025-01-01 and ends 2025-03-31 and is 0% completed
[D3.3 Technical architecture document pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed [D3.2 Pilot program proposals] as [c2] starts at [c1]'s end and ends 2025-05-31 and is 0% completed
[D3.4 Nix service flakes, packages and services for pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed [D3.3 Technical architecture document pilot programs] as [c3] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.5 CI/CD setup for pilot programs] starts 2024-12-02 and ends 2025-05-30 and is 0% completed [D3.4 Nix service flakes, packages and services for pilot programs] as [c4] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts 2025-05-01 and ends 2026-10-30 and is 0% completed [D3.5 CI/CD setup for pilot programs] as [c5] starts at [c2]'s end and ends 2025-12-31 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c3]'s end and ends 2026-10-30 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c4]'s end and ends 2026-10-30 and is 0% completed
[D3.6 Running Fediverse software for public organisations advisory] starts at [c5]'s end and ends 2026-10-30 and is 0% completed
-- WP4 Open calls and grant management -- -- WP4 Open calls and grant management --
[M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed [M2 Announcement open call] starts 2023-12-29 and requires 7 days and is 100% completed
@ -53,7 +57,7 @@ projectscale monthly
-- WP6 Outreach and Dissemination -- -- WP6 Outreach and Dissemination --
[D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red [D6.1 Communication strategy] starts 2023-12-01 and ends 2024-01-31 and is colored in Red
[D6.2 Media package] starts 2024-05-01 and ends 2024-07-31 and is colored in Red [D6.2 Media package] as [f2] starts 2024-12-01 and ends at [c1]'s start and is 0% completed
[D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed [D6.3 Communication report first period] starts 2025-03-03 and ends 2025-04-30 and is 0% completed
[D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed [D6.4 Communication report second period] starts 2026-09-01 and ends 2026-10-30 and is 0% completed
@endgantt @endgantt